Tender addenda shouldn't cost you a night: how Estimator+ does it
An addendum lands on Thursday arvo. In Estimator+ you drop it in the tender folder, Claude or ChatGPT swaps in the new revisions, the takeoff works off the current set and the affected subbies get revision notes.
In short
- An addendum shouldn't cost you a night. In Estimator+ you drop it in the tender folder and tell Claude or ChatGPT. It reads the addendum, matches each new revision to its old drawing, uploads the new drawings and supersedes the old ones.
- The takeoff works off the current revision of every sheet and applies each addendum before it measures, so a deleted wall or a changed door type never reaches the quantities.
- Subbies on an affected trade get clear revision notes for their trade on the Sendout link they already have.
- When a quantity moves, a rate follows it and a lump sum stays on the quantity it was priced on. That tells you which quotes need a call.
- Any past revision of your submission opens as a full workspace, so you can see what changed.
Why does an addendum still wreck your week?
An addendum shouldn't cost you a night. In Estimator+ you drop it in the tender folder, tell Claude or ChatGPT it's there, and the AI does the document control: it works out which drawings changed and swaps them in. Your evening goes on what the changes do to the price.
You know how it goes. It's Thursday arvo, the tender closes Tuesday, and Addendum 02 lands with six revised drawings and a two-line transmittal. Now someone has to work out which sheets changed, swap them in, check every quantity they touched and let the right subbies know.
None of that is hard. It's fiddly, though, and fiddly is where the mistakes hide. The expensive one is a takeoff or a subbie still working off Rev C after Rev D is out. That's how a wall the architect deleted on Thursday ends up in your price on Tuesday.
What happens when you drop it in the folder?
Estimator+ connects to your tender folder, the one on your computer. For most builders that's the company-drive folder synced to it, something like D:\Tenders\Riverbend Aged Care. When Addendum 02 arrives, you save it where you'd normally put it, say Addenda/Addendum 02, and tell the AI it's in.
It reads the addendum, matches each new revision to its old drawing, uploads the new drawings and supersedes the old ones. The takeoff and the subcontractors work off the current set from then on.
A couple of things it won't do. It never moves, renames or deletes your files, so Addendum 02 stays exactly where you saved it. The only place it writes is the _Estimator+ folders it keeps inside the tender folder.
If the addendum revises a spec section or a schedule, that stays on your drive too, and the AI reads it there with the rest of the specs. Estimator+ holds the sheet pictures, the measurements and the estimate.
How does the takeoff stay on the current set?
Before the AI measures a line, it reads the specification, schedules, general notes, contract terms, project scope and every addendum. Then it measures the current revision of every sheet, with each addendum applied first. So a wall Addendum 02 deleted never gets drawn, and a door that changed type gets counted as its new type.
Here's the bit that makes checking it bearable. The AI never types a quantity. Every quantity is a shape (an outline, a line, a dot) or a pin on a published sheet, and Estimator+ works out the number from that shape and the sheet's printed scale. After an addendum you're looking at shapes on Rev D, with each line's name sitting on the plan.
It also flags where two drawings disagree, which happens a lot with addenda. A plan gets reissued and the elevation showing the same window doesn't. The AI assumes, says what it assumed and keeps going, then asks you the open questions together at the end.
Example: Addendum 02 and its six drawings
This one's made up. A three-storey medical centre, closing Tuesday, and Addendum 02 revises six drawings. Each new revision gets matched to its old drawing and uploaded, and the old one's superseded. Here's what each change means after that.
| Drawing | What Addendum 02 changes | What the takeoff does | Revision notes go to |
|---|---|---|---|
| A-101 Ground floor plan, Rev C to D | Deletes the partition between consult rooms 3 and 4 | Measures Rev D, so the wall never reaches the wall linings | Plasterboard |
| A-102 Level 1 plan, Rev C to D | Changes door 1.07 from type D2 to fire-rated type D5 | Counts door 1.07 as a D5 | Doors and hardware |
| A-201 Elevations, Rev B to C | Widens window W05 | Takes W05 at its new width, and flags that A-101 Rev D still shows the old opening | Windows |
| A-301 Section A, Rev B to C | Swaps the void balustrade from glass to steel | Puts the balustrade on the steel line | Balustrades |
| A-510 Wet area details, Rev A to B | Revises the shower hob and upturn detail | Reads the new detail before measuring the waterproofing | Waterproofing |
| S-101 Ground slab plan, Rev 2 to 3 | Adds a slab set-down at the entry | Measures the slab off Rev 3 | Concrete |
Six trades get a revision note for their trade, on the link they already have. The W05 question goes in the list at the end, so you can send it to the architect with everything else.
Lump sum or rate: which one moves?
This is where an addendum actually costs money. Take that deleted partition. Say the wall linings line came to 412 m² on Rev C. The wall was 6.0 m long and 2.7 m high, lined both sides, so 32.4 m² comes out and the line measures 379.6 m² on Rev D.
Two plasterers priced it, ex GST. One gave you a lump sum of $19,776, worked out on the 412 m². The other gave a rate of $46.50 a m², which came to $19,158 on Rev C.
In Estimator+ a rate follows the live quantity, so the second quote now reads $17,651.40 on the 379.6 m². A lump sum stays fixed to the quantity it was priced on, so the first one still says $19,776 against 412 m². That's your cue to ring them. They might sharpen it, or tell you the wall was never in their number. Either way, the call's yours.
By the time you ring, they've already got the revision note on their Sendout link. Estimator+ never sends mail itself, so if you want them to hear about it this arvo, that's an email from your own inbox. The AI drafts reminders in your Outlook or Gmail and you press send.
What about revising your own price?
Sometimes the addendum lands after you've submitted, or the client comes back with questions and you put in a revised price. Your submission goes out as a branded PDF with a revision number on it, and every past revision stays open to you as a full workspace.
So when the client's QS asks why Rev 1 came in lower than Rev 0, you open Rev 0, see what changed and answer properly, without rebuilding the story from a pile of emails.
So what's the catch?
A few honest ones.
- You still tell it. The flow is: drop the addendum in the folder, then tell Claude or ChatGPT it's there.
- It reads PDF drawings, not CAD or BIM models. A revision that only turns up as a model file is one for you.
- It doesn't make the money calls. Which lump sum to chase, and whether to carry a subbie's old price, is still you.
- You check its work, right off the current sheet, where every shape carries its line's name.
If you want the rest of the tender picture, our posts on comparing subcontractor quotes and tender exclusions and qualifications pick up from here. And the AI takeoff post goes deeper on how the measuring works.
Got an addendum-heavy job on right now? Book a demo and we'll run the takeoff on one of your tenders, at your office or on Google Meet.
Frequently asked questions
What is a tender addendum?
A tender addendum is a formal change to the tender documents issued before tenders close, usually revised drawings, spec changes or answers to tenderers' questions. Every tenderer is meant to price it, and tender forms usually ask you to acknowledge each one.
What happens to my takeoff when an addendum comes in?
In Estimator+ you drop the addendum in the tender folder and tell Claude or ChatGPT. It matches each new revision to its old drawing, uploads the new drawings and supersedes the old ones. The takeoff works off the current revision and applies each addendum before measuring, so deleted or changed work never reaches the quantities.
How do subcontractors find out about an addendum?
Each subcontractor has one Sendout link for the job, and addenda add clear revision notes for the affected trades on it. Estimator+ never sends mail itself, so any email about the addendum comes from your own Outlook or Gmail, drafted by the AI and sent by you.
Does a lump sum quote change when the quantity changes?
No. In Estimator+ a lump sum stays fixed to the quantity it was priced on, and a rate follows the live quantity. After an addendum, the lump sums priced on an old quantity are the ones worth a phone call.
Can I see what changed between revisions of my tender price?
Yes. Each submission carries a revision number, and you can open any past revision as a full workspace and see what changed.